After the inspection of the engineering team, the replacement plan for the bridge bearing was determined. First, the bridge piers are reinforced as a whole, and then the bridge is lifted as a whole by placing hydraulic jacks on the bridge piers to complete the replacement of the auxiliary road bridge and the lifting of the main bridge body. It is expected that the auxiliary road bridge will pass in 30 days, and then closed. The main bridge, and finally completed the replacement of the main bridge bearing and the restoration of the auxiliary works. Through the synchronous lifting system provided by Jiangsu Canete, the bridge was finally successfully lifted as a whole, and the displacement and stress of the beam body were not.