Pakistan U-beam fine-tuning using two-dimensional adjustment hydraulic jack

Lahore Rail Transit Orange Line Project Site

At the site of the Lahore Rail Transit Orange Line project in Pakistan, Canete's 4-point PLC intelligent control synchronous lifting hydraulic system and two-dimensional adjustment hydraulic jack were used to provide technical guidance for U-beam fine-tuning.

The Orange Line project of Lahore Rail Transit is the first project in the history of Pakistan. The line is roughly north-south, with a total length of about 25.58km, a total of 26 stations, and a maximum train speed of 80km/h. The successful completion of this project will provide Pakistani people with safe, convenient and modern transportation services.

Canete is willing to make great contributions to the infrastructure construction of countries along the Belt and Road"!

Use 4-point intelligent control synchronous lifting hydraulic system to fine-tune the U-beam

U-beam fine-tuning

U-beam fine-tuning

Two-dimensional adjustment hydraulic jack fine-tuning site